Project Views

As projects are time-sensitive, we need different kind of views to convey information in a visual manner to users viewing them.

Apart from the generic list and report views for projects and tasks, ABNERP also provides Gantt, Kanban, and Calendar views for tasks. You can access these views by going to the Task list and selecting them via the left sidebar.

Gantt View

A Gantt Chart shows how tasks are linked to each other and shows their execution sequence, based on start and end dates set in the tasks along with any dependencies, if available.

Gantt Chart View

You can update the range of the chart by selecting one of Quarter Day, Half Day, Day, Week, or Month.

Dragging a task along the dates will update the start and end date of a task.

If you want to further customize the chart and make it more colorful, read this article

Kanban View

Kanban in Japanese means \